Ballesteros García, Ignacio (2013). Análisis de las voladuras realizadas en el centro minero Moró. Proyecto Fin de Carrera / Trabajo Fin de Grado, E.T.S.I. Minas (UPM).
Title: | Análisis de las voladuras realizadas en el centro minero Moró |
---|---|
Author/s: |
|
Contributor/s: |
|
Item Type: | Final Project |
Date: | July 2013 |
Subjects: | |
Faculty: | E.T.S.I. Minas (UPM) |
Department: | Ingeniería Química y Combustibles [hasta 2014] |
Creative Commons Licenses: | Recognition - No derivative works - Non commercial |
|
PDF
- Requires a PDF viewer, such as GSview, Xpdf or Adobe Acrobat Reader
Download (2MB) | Preview |
|
![]() |
Archive (ZIP)
Download (25MB) |
En este proyecto se analizan seis voladuras realizadas en el Centro Minero Moró (CM Moró) perteneciente a la empresa SIBELCO HISPANIA S.A., situado en la localidad de San Juan de Moró (Castellón). Se analizan las principales diferencias de las voladuras, con respecto a las fases de avance donde se encuentran, el tipo de material volado, la presencia de agua en las mismas, variación de consumo de explosivo y toneladas de roca arrancada. Tomando como base las normas de SIBELCO HISPANIA S.A., el proyecto define la evolución histórica de la empresa, las normativas de seguridad y salud, el ciclo de explotación en el CM Moró, ya que el proceso de arranque tanto de estéril (arenisca y caliza) como de arcillas, se desarrolla por completo mediante voladuras y finalmente un descripción más extensa y concisa de las mismas. ABSTRACT The project presents a comparative study of six blasts realised in the Centro Minero Moró (CM Moró) owned by SIBELCO HISPANIA S.A., located in San Juan de Moró (Castellón). A series of calculations have been conducted and graphs created to observe the main differences between the blasts, with respect to the stage to which it has advanced, the presence of water therein, variation in explosive consumption and tonnes of extracted rocks. Taking the standards of SIBELCO HISPANIA S.A. as a basis, the project defines the historical evolution of the business, the health and safety regulations, the extraction cycle in the CM Moró, since both the sterile (sandstone and limestone) and the clay extraction process are fully achieved by blasts. Ultimately, the aim is to attain a more extensive description of the latter
Item ID: | 21590 |
---|---|
DC Identifier: | https://oa.upm.es/21590/ |
OAI Identifier: | oai:oa.upm.es:21590 |
Deposited by: | Biblioteca ETSI Minas y Energía |
Deposited on: | 12 Nov 2013 12:47 |
Last Modified: | 24 Jan 2023 15:05 |